Asbestos/Asbestos-like material removal
Are you going to remove asbestos or asbestos-like material? If so, you must always make a notification. Even if you are allowed to build or renovate without a permit, you must report any asbestos that is released. Only after approval can you start your work!
The demolition notification is done at least 4 weeks before you start removing asbestos. In some cases, this is 5 working days.
Report removal of asbestos/asbestos-like material (file demolition notice)
As a resident, you may personally remove and dispose of up to 35 square meters (m2) of asbestos per residential address (parcel). This 35 m2 applies in total over all years of the residential address (parcel). You may not remove more than 35 m2 of asbestos yourself. For that, you must hire a specialized company.
Questions?
For questions about demolishing asbestos and submitting a demolition notification through the environmental counter, please contact the Building and Wenjen counter. You can also make an appointment to stop by or email frontofficeruimteTD@t-diel.nl.